Turn scope creep into a change order.

Price out-of-scope requests, see the margin you'd lose, and get a client email and formal summary ready to send. No sign-up needed.

Additional hours by role
Unbilled cost
£2,930
24.4% of fee leaking
Change order quote
£3,370
incl. £440 buffer
Delivery delay
+6 days
15% of timeline
Revised total
£15,370
36 extra hours

Ready to discuss the extra work? Copy the client email below, review the scope and agree the next step before adding more hours.

Start a 14-day free trial

Client email

Subject: Website redesign: proposed change order for new requests

Hi Acme Corp team,

Thanks for the new ideas over the last few weeks. We love the momentum, and we want to make sure each one gets the time it deserves.

A few of the recent requests sit outside the scope we agreed at the start:
  • Add a blog section with 3 templates
  • Third revision round on homepage
  • Integrate booking widget

To deliver these properly, we estimate 36 additional hours across the team. That comes to £3,370 as a change order, and would move the delivery date by about 6 working days.

You have three options, and any of them is fine with us:
  1. Approve the change order and we add these to the current plan.
  2. Swap them for items in the original scope of similar size.
  3. Park them for a phase 2 after launch.

I've attached a one-page summary. Happy to walk through it on a quick call this week.

Best,
[Your name]

Negotiation script

NEGOTIATION SCRIPT

Open: "Before we dig in, I want to flag something so there are no surprises later."
Frame: "These requests are great additions. They weren't in the original brief, so I want to scope them properly rather than rush them."
Number: "It's 36 hours of work, £3,370, and roughly 6 extra working days."
Options: "We can add it, swap it for something already planned, or park it for phase 2."
If they push back on price: "I can drop the lowest-priority item to bring it down. Which one matters least to you?"
If they ask to absorb it: "We've already absorbed a few small things. For this size, absorbing it would mean cutting corners on what you've paid for."
Close: "Which option works best? I'll send the updated plan today."

Formal change order

CHANGE ORDER SUMMARY
Client: Acme Corp
Project: Website redesign
Date: 27/10/2026

ORIGINAL SCOPE
Homepage and 5 inner page designs, 2 revision rounds, responsive build, CMS setup.
Original fee: £12,000  ·  Timeline: 8 weeks

ADDED SCOPE (NOT IN ORIGINAL AGREEMENT)
  1. Add a blog section with 3 templates
  2. Third revision round on homepage
  3. Integrate booking widget

COST BREAKDOWN
  Designer                  14 h × £75/h  = £1,050
  Developer                 18 h × £90/h  = £1,620
  Project manager            4 h × £65/h  = £260
  Subtotal                  36 h              = £2,930
  Contingency (15%)                         = £440
  CHANGE ORDER TOTAL                         = £3,370

TIMELINE IMPACT
  +6 working days (15% of original timeline)

REVISED PROJECT TOTAL: £15,370

Approved by (client): ____________________   Date: __________
Approved by (agency): ____________________   Date: __________
Your next step

Put a next step against the extra work.

You have a priced change order. Flow Pilot brings recorded client context and outstanding work into a daily queue so your team can review, assign and follow up.